Development Approval obtained from Western Downs Regional Council

About
Project Timeline
Grid connection agreement with Powerlink
Hana Financial Investment engage with Luminous Energy to acquire 100% of the Project
Hana Financial Investment mandate awarded
Project Finance syndication launched
Foreign Investment Review Board (FIRB) approved
Hana Financial Investment complete acquisition of the Project
Share Purchase Agreement signed
Power Purchase Agreement signed with CS Energy
Sterling & Wilson engaged as EPC and O&M Contractor
Financial Close is reached and Notice to Proceed issued to Sterling & Wilson
First generation sent to the grid (target)
Commercial Operation Date (target)